JLR has opened a solar farm the size of 36 football pitches at its Gaydon headquarters as part of efforts to increase its energy independence.
The 26-hectare, 18MW site can generate enough electricity to power a third of the Jaguar and Land Rover base. The site is home to JLR’s design, engineering and R&D teams.
It's part of a move by JLR to source at least 30% of its global energy use from on-site renewables, reducing its reliance on grid energy – and therefore fluctuating energy costs – and lessening its environmental impact.
A similar project is being completed at JLR's Wolverhampton Electric Propulsion Manufacturing Centre.
One of the UK’s largest rooftop arrays, featuring more than 18,000 panels, will open there in the coming months.
This will be able to generate around 9500 MWh of energy each year, meeting 40% of the site’s needs.
Next year, JLR will install 10MW of solar car ports at its Merseyside site. These include canopies and solar walkways, which are quite common in hotter countries, such as Spain. They will mostly provide energy for EV charging.
JLR sustainability chief Andrea Debbane said the steps were “important", because "they directly reduce our global operational emissions and help move us closer to our net-zero goal, whilst delivering tangible value today and for the long term.”